STATUS: CONSTRUCTION ANTICIPATED TO BEGIN MARCH 20, 2023

Latest Update (03/07/2023)

2nd Street Road Closure Map

The following information is being released by JR Civil of Montana as a Public Advisory. 

FULL ROAD CLOSURE: Work Area 3-1: Intersection of 2nd St E and the alleyway between 4th Ave E and 5th Ave E  

Start Date and Duration: Work to commence on 3/20/23. Tentatively anticipate 5 days to complete this work. 

GENERAL NOTES: Through traffic at this intersection along 2nd St E and the associated alleyway will not be permitted. Access to residences will remain available.  

QUESTIONS/CONCERNS: For any questions or concerns, please call Alex at 406-259-3741 

5th Alley EN Sewer Main Replacement Project Map

Project Description:

The City of Kalispell has selected JR Civil to replace sewer main from 4th Ave EN (north of Parkline Trail) to East Center Street, along East Center Street to 5th Alley EN (alley between 4th Ave E and 5th Ave E), and along 5th Alley EN from Center Street to south of 6th St E.  

The work is planned to start in March 2023 and is expected to last until (90 Calendar Days).  NorthWestern Energy will be relocating the gas main in the Alley, from 2nd St E to 6th St E. The gas relocation work is planned to start as early as possible in the Spring of 2023.   Work will begin at approximately 7:00 am and continue to 5:00 pm each day, Monday through Friday.

Work occurring in 4th Ave EN and along East Center St will maintain two-way traffic with one lane traffic controls in place.

Work occurring in the Alley will require sections of the Alley be closed to traffic.  Solid waste containers will be relocated to the street at ends of the alley and moved back into the alley at the completion of construction. Residents who access their driveways in the alley will need to find alternate parking areas on side streets during this time.